You finished the job, the subbie wants their money, and you are holding cash retention because the contract says you can. It feels like a simple bookkeeping matter. Then you learn that on certain contracts, that money does not belong in your everyday account at all. A QBCC retention trust account may be required, and getting it wrong puts both your cash flow and your licence on the line.
If that sounds like one more piece of QBCC paperwork you did not see coming, you are not alone. Most contractors we speak to are across variations, deposits and renewals, but trust accounts sit in the Building Industry Fairness (Security of Payment) Act, and they rarely get explained in plain English. Let’s fix that.
What a QBCC retention trust account actually is
Retention is money a head contractor or principal withholds from a payment as security until the work is completed or defects are fixed. Under the BIF Act, where a project trust applies, cash retentions must be held in a retention trust account until they are due to be paid. The money is held for the contracted parties, such as your subcontractors, and for you as trustee.
One detail surprises people: you only need one retention trust account. It can hold retentions across multiple qualifying contracts, so you are not opening a new account for every job.
Who is caught, and who is not
According to the QBCC, retention trust accounts are required for head contractors and private sector principals where the head contract needs a project trust account. Since 1 January 2022, that includes private principals withholding from head contractors. Commonwealth, Queensland Government, state authority and local government parties are exempt, and a trust is only needed where cash retention is withheld.
The project trust side is driven by contract size. From 1 January 2022, project trusts apply to contracts of $1 million or more for Queensland Health and Hospital Services, and $10 million or more for state authorities, local governments and private entities (all excluding GST). Contracts under $1 million cannot use project trust accounts. Other contracts fall outside the regime, including those with practical completion under 90 days and, generally, subcontracts unless the parties are related entities.
So, who should be checking their position?
- Head contractors on large private or commercial builds who hold cash retention from subcontractors
- Subcontractors at any tier where the head contract requires a project trust
- Contractors working with related-entity subcontractors
- Contractors who have never assessed their contracts against the criteria at all
The 5-day rules that trip people up
The QBCC trustee guide sets out a tight timeline. We know that reading a list of deadlines when you are already juggling site work is exhausting, so here is the short version in order:
- Open the account at a QBCC-approved financial institution before withholding any eligible amount. The account name must include your name and the word “trust”.
- Notify the QBCC within 5 business days of opening, online or by Form TA1.
- Tell the contracted party in writing before you withhold, or within 5 business days of opening if the account came later.
- Deposit each retention immediately by traceable electronic payment, and give written notice of the deposit within 5 business days.
- If you withheld retention before the account existed, deposit that amount within 5 business days of the trust becoming required.
Keeping the books straight once the money is in
Opening the account is the easy part. The ongoing record keeping is where small businesses slip. The QBCC guide requires a trust ledger with each transaction recorded in date order within 3 business days, a monthly reconciliation within 5 business days after month end, and all trust records kept for at least 7 years.
Money can only go out to beneficiaries, to the account they nominate. You can pay yourself for defect rectification only after the defects liability period ends, though you can pay another party to fix defects at any time. Trust funds cannot be invested, and a shortfall must be covered from your own funds straight away. If you take money out in error, repay it as soon as practicable and notify the contracted party within 5 business days.
Why the stakes are higher than a late invoice
The QBCC can investigate, direct trustees and prosecute alleged offences, including investing trust funds or closing an account while the trust is still required. Separately, failing to release a retention amount without a reasonable excuse can attract up to 200 penalty units or one year’s imprisonment. The commissioner can also freeze trust accounts and require an account review report in situations such as contract termination, insolvency or a suspended or cancelled trustee licence.
That last point matters if you already feel the QBCC is watching your every move. Trust account problems rarely arrive alone. They tend to surface when a subbie complains, a project stalls or a licence is already under review.
“Most trust account breaches we see are not deliberate. The contractor simply never worked out whether the contract triggered a trust in the first place.”
Karen Zhang, QBCC Express Founder
Get a second set of eyes before it becomes a problem
If you are holding retention now and are not sure whether a trust account applies, the safest move is to stop and assess before the next payment run. Our team works through contract thresholds, related-entity rules and your licence position with you, so you know exactly where you stand. Book a Strategy Session and we will map out what you need to fix and in what order.
Trust obligations also sit alongside your financial standing as a licensee. If you are a company, make sure your nominee and supervisor eligibility are in order too, because a licence under pressure is harder to defend.
The bottom line
A QBCC retention trust account is about protecting other people’s money, and the QBCC treats it that way. Assess your contracts, open the account before you withhold, hit the 5 business day deadlines and keep clean records. If any of that feels uncertain, do not wait for a complaint to find out. Contact QBCC Express for a Strategy Session today.
Frequently Asked Questions
Do I need a separate retention trust account for every job?
No. Each trustee needs only one retention trust account, and it can hold retentions across multiple qualifying contracts. Project trust accounts are different, with one required per eligible contract.
Does a retention trust account apply if I hold a bank guarantee instead of cash?
No. The retention trust requirement applies only where cash retentions are withheld. Other securities such as bank guarantees are dealt with under the retention provisions of the QBCC Act.
Are government projects covered?
Commonwealth, Queensland Government, state authority and local government parties are exempt as the contracting party holding retention. Head contractors working for private principals on qualifying contracts are the main group affected.
How long must I keep trust account records?
The QBCC trustee guide requires trust records to be kept for at least 7 years, in Australian dollars and in English. You must also keep evidence of any delegation for 7 years.
Can I use retention money to pay for defect repairs?
You can pay another party to correct defects at any time. You can only pay yourself for defect rectification after the defects liability period has ended.